深厚砂层坝肩绕坝渗流规律及防渗方案研究
引用本文:吕海东,王瑞骏,李章浩.深厚砂层坝肩绕坝渗流规律及防渗方案研究[J].西北农林科技大学学报(社会科学版),2006,34(12):215-220.
作者姓名:吕海东  王瑞骏  李章浩
作者单位:1. 西安理工大学,水利水电学院,陕西,西安,710048
2. 云南金沙江中游水电开发有限公司,云南,昆明,650051
3. 中国水电顾问集团成都勘测设计研究院,四川,成都,610072
摘    要:为了研究深厚砂层坝肩绕坝渗流的规律,结合拟建的陕西省王圪堵水库土石坝工程,进行了左坝肩绕坝渗流的三维有限元分析,并以坝肩砂层渗透稳定为控制条件,进行了防渗墙延伸长度方案的比较研究,同时对传统的绕坝渗流计算方法水力学法所存在的问题进行了分析。结果表明,水力学法计算的绕坝渗流量结果偏小,据其进行防渗墙延伸长度方案的比较与选择缺乏理论依据;绕坝渗流沿河道方向的影响范围是有限的,主要影响发生在坝趾处的左岸坡上;随着防渗墙延伸长度的增加,坝趾处左岸横断面砂层的最大渗透坡降及出逸面的渗透坡降均逐渐减小;深厚砂层坝肩的绕坝渗流主要发生在砂层内,且随着防渗墙延伸长度的增加,砂层及左坝肩整体的绕坝渗流量均逐步减小,但差异不显著。

关 键 词:深厚砂层  坝肩  绕坝渗流  防渗墙延伸长度方案  有限元分析
文章编号:1671-9387(2006)12-0215-06
收稿时间:2006-05-10
修稿时间:2006年5月10日

Finite element analysis of bypass abutment seepage in deep and thick sand layer
LU Hai-dong,WANG Rui-jun,LI Zhang-hao,WANG Dang-zai.Finite element analysis of bypass abutment seepage in deep and thick sand layer[J].Journal of Northwest Sci-Tech Univ of Agr and,2006,34(12):215-220.
Authors:LU Hai-dong  WANG Rui-jun  LI Zhang-hao  WANG Dang-zai
Institution:1 Institute of Water Resources and Hydro-electric Engineering,Xi’an University of Technology,Xi’an,Shaanxi 710048,China;2 Yunnan Jinshajiang Mid-stream Hydroelectric Development Company,Kunming,Yunnan 650051,China;3 Chengdu Hydroelectric Investigation & Design Institute,China Hydropower Consulting Group,Chengdu,Sichuan 610072,China)
Abstract:Three-dimensional finite element analysis of left dam abutment seepage is carried out based on a proposed earth dam in order to study the bypass seepage law of deep and thick sand layer.With the sand layer's seepage stability as control condition,cutoff wall extending length scheme is comparatively studied,and the problem in the traditional hydraulic method is also analyzed.The result shows that the dam bypass seepage quantity using hydraulic method is small,virtually the comparison and selection for cutoff wall extending length scheme is short of theory gist.The influence of bypass seepage is limited along the direction of river stream,but the effect on the left bank around the dam toe is great.With the increase of cutoff wall's extending length,maximum seepage gradient of sand layer and seepage gradient of exit surface gradually decrease in the cross section of left bank near the dam toe.Bypass seepages mostly occur in deep and thick sand layer of dam abutment,moreover with the increase of cutoff wall's extending length,bypass seepage quantity in sand layer and the whole left dam abutment gradually decreases,but without remarkable difference.
Keywords:deep and thick sand layer  dam abutment  bypass seepage  cutoff wall's extending length scheme  finite element analysis