铅厂水电站RCC重力坝施工期温控方案研究
引用本文:王静.铅厂水电站RCC重力坝施工期温控方案研究[J].中国农村水利水电,2012(5):150-154.
作者姓名:王静
作者单位:云南省水利水电勘测设计研究院,昆明,650021
摘    要:铅厂水电站RCC重力坝上升速度快,为解决温控问题,施工期间结合现场混凝土试验结果和气象实测资料,选择溢流坝段作为代表坝段,对7组温控方案进行三维有限元仿真分析计算,根据最高温度、基础温差、超标拉应力范围和大小等计算结果综合分析,推荐控制20℃的混凝土浇筑温度+通16℃冷却水实施方案,取得较好的效果。

关 键 词:浇筑温度  基础温差  冷却水  超标拉应力

Research on the Temperature Control Program of RCC Gravity Dam of Qianchang Hydroelectric Power Station
WANG Jing.Research on the Temperature Control Program of RCC Gravity Dam of Qianchang Hydroelectric Power Station[J].China Rural Water and Hydropower,2012(5):150-154.
Authors:WANG Jing
Institution:WANG Jing(Yunnan Water and Hydropower Engineering Investigation,Design and Research Institute,Kunming 650021,China)
Abstract:The height of RCC gravity dam of Qianchang Hydroelectric Power Station is growing fast during the construction period,thus temperature control is significant for the construction of the whole dam.In order to solve the problem mentioned above,considering the results of concrete in-situ test and the local meteorological data,overflow section is chosen to analyze as typical section and seven temperature control plans are proposed.According to the results of 3D FEM simulation and analysis of each plan,and based on a comprehensive analysis of the highest temperature,basic temperature difference,excessive tensile stress range and value etc,control temperature of concrete placing is 20 centigrade degree and the temperature of cooling water is 16 centigrade degree.Under this condition the result is good.
Keywords:placing temperature  basic temperature difference  cooling water  excessive tensile stress