考虑分布式电源的农村配电网网络重构
引用本文:高 燕,杨仁刚,李伟.考虑分布式电源的农村配电网网络重构[J].农业工程学报,2013,29(9):162-169.
作者姓名:高 燕  杨仁刚  李伟
作者单位:1. 中国农业大学信息与电气工程学院,北京100083
2. 北京电力经济技术研究院,北京100075
基金项目:国家"863"计划,(2012AA050217)
摘    要:分布式电源接入农村配电网改变了农网的网络结构和运行方式,辐射结构是农电网运行、保护和调度的基础.该文建立了考虑分布式电源的配电网重构非线性整数优化数学模型,引入离散的二进制决策变量表示配电网的支路状态,建立了严格的数学模型保证配电网的辐射运行,提出分支定界法结合原始对偶内点法精确求解农村配电网网络重构,通过对分支节点检测,去掉不可行节点;通过增加安全因子,避免混合非线性整数规划陷入局部最优.结果表明该方法是一种可行的配电网重构方法,可为农村配电网最优运行提供参考.

关 键 词:农村地区  发电  电源电路  网络重构  分布式电源  内点法  分支定界法  节点检测
收稿时间:2012/11/23 0:00:00
修稿时间:2013/1/24 0:00:00

Rural distribution network reconfiguration with dispersed generation
Gao Yan,Yang Rengang and Li Wei.Rural distribution network reconfiguration with dispersed generation[J].Transactions of the Chinese Society of Agricultural Engineering,2013,29(9):162-169.
Authors:Gao Yan  Yang Rengang and Li Wei
Abstract:More and more Dispersed Generation has been interconnected with rural distribution networks and rural distribution networks commonly operate with a radial topology. Dispersed Generation is complicating the operation and protection schemes. But a radial distribution network is the basis of operation, protection schemes and dispatch in a rural distribution network. The models of distribution network reconfiguration should consider radial topology in their formulation. So the paper presented radial constraints in a mathematical model for a distribution network Reconfiguration and gave a preliminary analysis of radial constraints. Concerning an interconnecting Distributed Resource with an Electric Power System, mathematical models based on mixed integer nonlinear programming (MINLP) for the rural distribution network reconfiguration were built. The objective function was power losses of the distribution system. The binary nature of variables was proposed to represents the circuit between buses i and j connecting or not. Considering interconnecting with a substation for Dispersed Generation, a new constraint has been added to ensure that a distributed generator is not isolated from the substation. The mathematical model for distribution network reconfiguration problem was one in which the radial constraints were represented explicitly and showed that radial constraints can be considered in a simple and efficient way. With this method, distribution networks interconnecting as a Distributed Resource are still regarded as a passive termination of the distribution network with a radial structure. The paper proposed the use of a branch - bound method and Primal-dual interior point method to solve power dispatch and optimization reconfiguration problem of a distribution power system. The models of distribution network reconfiguration were formulated as a mixed integer non-linear programming (MINLP) problem. The MINLPIS relaxed, resulting in a set of non-linear programming (NLP) problems, which are solved at each node of the branch - bound tree through a Primal-dual interior point algorithm. The non-linear branch - bound algorithm proposed has special fathoming criteria to deal with non-linear and optimization reconfiguration models. The fathoming tests are redefined, adding a safety value to the objective function of each problem before they are fathomed through the objective function criteria, avoiding a convergence to local optimum solutions. From the result of the case study, it can be seen from the 33 nodes radial distribution test system that DG has the effects of a loss reduction improvement over feeders in the case, and the distribution system without DG are different from those with DG. With the increasing of capacity and numbers of DG, there has been a significant loss reduction and high efficiency of a distribution system with distributed generation (DG). The presented method has been compared with a GA algorithm based on the 54 nodes radial distribution test system The results show that solo transfer node can be identified by the presented method whereas by GA algorithm. The last case showed the total CPU time used by the branch - bound and Primal-dual interior point method and the number of binary variables for different test systems. The results showed that the presented method in this paper needs more time to obtain a global solution, but with the development of computer technology, the proposed method is a promising and effective tool for a distribution network with DG.
Keywords:rural area  power generation  power supply circuits  distribution network reconfiguration  DG  primal-dual interior point method  branch-bound method  fathoming tests